Filter Inspection and Test Plan

This content provides you with a example filter inspection and test plan. This is a draft filter ITP and must be modified based on your PO requirements. You may also read the pressure vessel ITP article for more information. There is a draft ITP there, you can download the ITP and use alongside of this ITP to support you to generate your own ITP based on your specifications.

Filter Inspection and Test Plan TaskVendorTPI InspectionClient
Filter Pre-inspection meeting, when specified by Purchaser/OwnerHHH
Filter Mill test reports including impact test and non-destructive test, when specifiedHW/RR
Filter Material identification and markingsHWR
Filter WPS/PQR, Welders qualifications (records or welder's list)HSR
Filter Weld preparation and fit-up, back chip inspectionHSR
Filter Execution of major repairs, when issued NCRHHR
Filter Visual and dimensional inspection prior to heat treatment, when applicableHSR
Filter Heat treatment record review, when applicableHRR
Filter Alloy verification, when specifiedHSR
Filter Ferrite check for weld, when specifiedHSR
Filter Non-destructive testing (RT, UT, MT, PT when applicable)HSR
Filter Review of radiographs, when applicableHSR
Filter Refractory anchor and lining inspection, when specifiedHSR
Filter Production weld test, when requiredHWR
Filter Hardness measurements in final condition, when specifiedHSR
Filter Visual and dimensional inspection during fabricationHWR
Filter Reinforcing pad air-soap testHSR
Filter Leak test for sleeve type nozzle, when applicableHSR
Filter Hydrostatic testHHR
Filter Installation of internals, when applicableHWR
Filter Other Job Requirement Inspection Record (when specified)HWR
Filter Surface preparation prior to painting, coating, liningHSR
Filter Complete draining and nitrogen filling or desiccant or volatile corrosion inhibitor treatment checkHSR
Filter Final visual inspection (including Painting (color & thickness), coating, preservation, lining, picking, nameplate, tagging, marking, and Aux items like spare parts, bolts, etc.)HHR
Filter Documentation review prior to release at local shop(Final activity of Technical Inspection)HHR
Filter Pre-shipment InspectionHHR

Filter Inspection and Test Plan Points

H: Hold Point implies that relevant production activities shall not proceed until the continuation of work is permitted by Purchaser. (Notification req'd)

W: Witness point implies that Purchaser intends to witness the designated inspection feature. If Purchaser decides not to

witness the relevant feature, production can proceed without permission of Purchaser. (Notification req'd)

S: Witness, but spot check basis. Initial operation will be witness point and subsequent operation will be witnessed at discretion of Purchaser

considering the results of previous inspection. (Random Inspection : Notification not req'd)

R: Review inspection & test records (Notification not req'd)

General Note for Filter ITP:

1) Filter Witness/hold point by Code Inspector, when applied by Code Stamp/Local Regulation, is to comply with its requirements and to specify in Vendor's ITP.

2) Type of Inspection by Filter Purchaser may be changed according to equipment criticality and vendor QC evaluation at job stage.

3) When requested in the requisition, detailed Filter ITP shall be submitted by Vendor.

4) Monitoring/Observation of Filter Vendor shop daily routine works (i.e. Storage of materials & welding consumables, Adherence to approved procedures, Testing tool calibration check, Welder/NDE Operator performance & qualification, workmanship, cleanliness and etc.) shall be done by Purchaser during inspection visit.

5) Filter Final Visual Inspection/Documentation Review/Pre-Shipment Inspection may be combined within one time visit.

 