Steam Trap Inspection and Test Plan 

This content provides you with a sample Steam Trap Inspection and Test Plan. This steam trap ITP is a draft and you need to modify it to meet your specifications.

Steam Trap Inspection and Test Plan TaskVendorTPI InspectionClient
Mill test reports including impact test and non-destructive test, when specifiedHHR
Material identification and markingsHW/RR
WPS/PQR, Welders qualifications (records or welder's list)HWR
Weld preparation and fit-up, back chip inspectionHSR
Execution of major repairs, when issued NCRHHR
Visual and dimensional inspection prior to heat treatment, when applicableHWR
Heat treatment record review, when applicableHWR
Alloy verification, when specifiedHWR
Ferrite check for weld, when specifiedHSR
Non-destructive testing (RT, UT, MT, PT when applicable)HSR
Review of radiographs, when applicableHWR
Production weld test, when requiredHWR
Hardness measurements in final condition, when specifiedHWR
Visual and dimensional inspectionHHR
Hydrostatic testHHR
Function TestHHR
Surface preparation prior to painting, coating, liningHWR
Complete draining and nitrogen filling or desiccant or volatile corrosion inhibitor treatment checkHWR
Final visual inspection (including Painting (color & thickness), coating, preservation, lining, picking, nameplate, tagging, marking, and Aux items like spare parts, bolts, etc.)HHR
Documentation review prior to release at local shop(Final activity of Technical Inspection)HHR
Pre-shipment InspectionHHR

Steam Trap Inspection and Test Plan Points

H: Hold Point implies that relevant production activities shall not proceed until the continuation of work is permitted by Purchaser. (Notification req'd)

W: Witness point implies that Purchaser intends to witness the designated inspection feature. If Purchaser decides not to witness the relevant feature, production can proceed without permission of Purchaser. (Notification req'd)

S: Witness, but spot check basis. Initial operation will be witness point and subsequent operation will be witnessed at discretion of Purchaser considering the results of previous inspection. (Random Inspection : Notification not req'd)

R: Review inspection & test records (Notification not req'd)

You need to add three more columns in above ITP, one for related construction code, the second one for acceptance criteria and third one for verifying documents.

Your acceptance criteria must meet your construction code. The verifying document must be fill out for each item in above ITP. These documents are inspection reports, test records, material certificates, test procedures, etc.

 